Candidate
of Science N. L. Batseva, student A. Kradetskaya
Tomsk
Polytechnic University, Russia
The
analysis of long-term steady states of Khakassia power system
Abstract
This
report provides the general analysis of 500/220 kV electrical networks of the
“Regional Dispatch Administration of Khakass power system” and also it is based
on calculated of steady-states regimes including taking into account future
development.
Keywords: Khakass power
system, Sayano-Shushenskaya hydroelectric power station, transmission line,
steady-states regimes.
I. Introduction.
The
Republic of Khakassia is located in the southwestern part of the Eastern
Siberia within the Sayano-Altaic mountain system. In the north and east
Khakassia boarders with Krasnoyarsk Krai and in the west – with Kemerovo
Oblast.
The
“Regional Dispatch Administration of Khakassia power system” situates directly
on the territory of Khakassia Republic and managers and supervises generating
objects with total install capacity of 7038 MW. The electric power sector of
Khakassia also includes 8, 33 and 47 overhead lines working at voltage of 500,
220 and 110 kV correspondingly. Total capacity of transformers installed in
substations is 19355 MVA.
In
the Republic of Khakassia the primary consumers are built on fabricators of
various industries. For the most part of Electrical energy users are heavy
engineering, coal mining, agribusiness, food industry companies and also
residential customers.
II. Statement of the problem.
The
Republic of Khakassia is the key power system in the aspect of electrical
energy generation from Sayano-Shushenskaya hydroelectric power station and load
peaks compensation on large territory of Siberian Federal District. In the east
it is adjacent to Krasnoyarsk power system and in the west – to Kuzbass. High
voltage lines working at 500 and 220 kV are the main inter-system links of
republic with the other energy system.
Power
system of Khakassia consists of the following main objects of generation:
- Sayano-Shushenskaya hydroelectric power station (the most powerful
station in Russia with installed capacity of 6400 MW);
- Mainskaya hydroelectric power station with installed capacity of 321 MW;
- Abakan thermal power station with installed capacity of 270 MW and also
two power stations (“Abaza-Energo” Ltd and “Sora” Ltd) with total installed
capacity of 25 MW.
Sayano-Shushenskaya
hydroelectric power station is the most powerful electric energy source within
the Russian and Siberian United Energy System that covers seasonal and daily
power deviations. The output of Sayano-Shushenskaya hydroelectric power station
provides the consumers of Khakassia with required electrical energy and power
via 500 kV transmission line Sayano-Shushenskaya – Oznachennoye – Abakan, and
also it is a source of electrical energy for the western deficient power
systems via 500 kV transmission line Sayano-Shushenskaya – Novokuznetsk.
Prior
to the well-known incident Sayano-Shushenskaya hydroelectric power station
generated jointly with Mainskaya hydroelectric power station 20-26 billion
kilowatt hours (kWh) of electricity per a year and their output was
approximately 4610 MW of power [1]. In winter it covered up to 5-15% of energy
consumption over Siberia; a lack of capacity from this station produces a power
deficit about 70 million kWh per a day.
Mainskaya
hydroelectric power station is the control compensating power station that
smoothes water level fluctuations in the river Yenisei which come from changing
of operational modes in Sayano-Shushenskaya hydroelectric power station.
Abakan
thermal power station is the main and the most important source of heat supply
in the Republic of Khakassia. Energy output within the power system of
Khakassia and connection with it is implemented via transmission lines working
at voltage of 110 and 220 kV. Transmission is realized with the help of 200 MVA
autotransformer by the 220 kV line Abakan-Rayonnaya substation – Abakan thermal
power station, and through the 110 kV electrical networks to Abakan-Rayonnaya
substation.
Transmission
lines working at voltage of 500 kV provide the power transfer both supplying
the Republic of Khakassia itself and carrying power flows between Khakass and
Krasnoyarsk power systems. According to this stability of the Siberian United
Energy System depends on reliability of these lines.
After
the incident at Sayano-Shushenskaya hydroelectric power station energy
consumption of Khakassia was dramatically higher in a comparison with the value
of generation. This resulted in a disturbance both in Khakass and adjacent
power systems.
III. Problem solution and results.
In
this regard a number of measures aimed to improve system sustainability and
stability in emergency situations was put forward.
First
of all, it is planned to install the fourth turbine generator at Abakan thermal
power station to cover the electrical loads growth in the zone of its proximate
influence. Secondly, it is worked out a project of building the second circuit
of the 500 kV transmission line Aluminievaya substation – Abakan substation–
Itatskaya substation in order to improve reliability of existing line.
Figure
1 shows the scheme of Khakass power system including 500/220 kV networks.
Calculations
of regimes were made with the help of the special software “MUSTANG”.
Substations junction nodes of 110 kV were taken into account as loads, network
reduction was not made in order to achieve more reliable values of intra- and
inter-system power flows.
The
results of calculations for existing and advanced schemes are presented in
Tables 1 and 2. It is important to mention that these results were obtained
considering reactor conductivities in calculations in order to prevent voltage
reduction and keep its level according to required values. There were installed
two groups of single-phase reactors on the buses of Abakan and Sora
substations. This control measure helped to supply the necessary voltage level
directly in these substations and also in the zone of Tuim substation taps.
Figure 1 – The scheme of
500/220 kV electrical networks of Khakassia before reconstruction
Table 1 – Node calculations
The name of substation |
Designed voltage, kV (existing scheme) |
Designed voltage, kV (advanced schemes) |
Sayano-Shushenskaya hydroelectric power station 10 êV |
15,75 |
15,75 |
Sayano-Shushenskaya hydroelectric power station 500
kV |
513,90 |
518,70 |
Oznachennoye 500 kV |
512,81 |
519,10 |
Aluminievaya 500 kV |
510,33 |
513,99 |
Abakan 500 kV |
500 (swing-bus) |
500 (swing-bus) |
Abakan-Rayonnaya 220 kV |
241,59 |
200,63 |
Abakan thermal power station 220 kV |
240,73 |
199,58 |
Table 2 – Branch calculations
The name of
transmission line |
Designed current, kA |
Permissible current,
kA |
The scheme condition |
Sayano-Shushenskaya –
Oznachennoye 500 kV |
0,63 |
0,945 |
existing scheme |
Aluminievaya – Abakan
500 kV |
1,47 |
0,825 |
|
Abakan thermal power
station – Abakan-Rayonnaya 500 kV |
0,34 |
0,825 |
|
Sayano-Shushenskaya –
Oznachennoye 500 kV |
0,63 |
0,945 |
advanced schemes |
Aluminievaya – Abakan
500 kV (the first circuit) |
0,8 |
0,825 |
|
Aluminievaya – Abakan
500 kV (the second circuit) |
0,67 |
0,825 |
|
Abakan thermal power
station – Abakan-Rayonnaya 500 kV |
0,59 |
0,825 |
IV. Summary.
Analyzing
the results there can be done the following conclusions:
1. Currently the existing 500 kV overhead line Aluminievaya substation –
Abakan substation – Itatskaya substation is extremely unreliable [2]; the
smallest system failures or emergency outage of this line will result in
disturbance of both intra- and inter-system energy transfer separating Khakass
and Krasnoyarsk power systems. Therefore construction of the second circuit
will have a positive effect redistributing existing power flows.
2. It should be mentioned that Khakass power system has quite enough
potential to add new generating capacities.
References
1.
Khakass power engineering before and
after breakdown // Power engineering. – 2010, ¹ 32. – P. 10-19.
2.
Reference document of electrical
networks designing / edited by D.L. Faibisovich. – Moskow: Publishing house
“ENAS”, 2006 – 320 p.