Òåõíè÷åñêèå íàóêè/5.
Ýíåðãåòèêà
Candidate of Science N.L. Batseva, student A.P.
Shubenkina
Tomsk Polytechnic University, Russia
The flux transfer in advanced
Tomsk interconnected power network
In Tomsk power system (PS) consumers are provided
electrical energy by 220kV double-circuit overhead line which begins on
Nizhnevartovsk Power Plant (PP) (Tyumen PS), passes via seven substations of
Tomsk PS: Sovietsko-Sosninskaya
– Chapaevka – Raskino – Vertikos – Parabel – Chazhemto
– Volodino and ends on Tomskaya substation (further Nizhnevartovsk PP –
Tomskaya). The length of this line is 800 km, and nowadays it is operating as
no-load line between substations Vertikos and Parabel (figure 1).
Figure 1 – The fragment of
Tomsk interconnected power network with no-load line
This fact leads to the power supply deterioration of
oil and gas industry consumers (single-way feed from Tyumen PS); unacceptable boosting or reduction of the voltage value on the
long-distance substation busbars.
Unfortunately it
is impossible to improve the power supply reliability by using Vertikos – Parabel line as the double-way feed line because of current overload in the main
line Nizhnevartovsk PP (Tyumen PS) – Sovietsko-Sosninskaya
under conditions of emergency or maintenance on one circuit the last (table 1).
Table 1 – Results of regime calculation under condition when Vertikos
– Parabel line is switched on two ends
Name of overhead line |
Wire mark |
Admissible continuous
current
I, À (outdoor) |
State of operation |
Current, A |
Nizhnevartovsk PP –
Sovietsko-Sosninskaya |
ÀS
240/32 |
610 |
Two circuits are in service |
346 |
One circuit is switched off |
611 |
One of ways to
redress situation is development of interconnected network by means of place
into service 500kV single-circuit overhead line Nizhnevartovsk
PP – Tomskaya till 2016 [1]. In practice, it
corresponds the case when 220kV overhead line will operate with 500 kV overhead
line in parallel.
According to the
results (table 2), under the condition of inherent power flowing via 220 kV and
500 kV overhead lines, the desired effect of improving power transmission
capacity is not observed: 500kV overhead line is underused but 220kV overhead
line operates under power transmission capacity limit, which leads to the
magnifying of total power and energy losses.
Table 2 – Power flows
under the condition of inherent power flowing
Name of overhead line |
Overhead line voltage, kV |
Power flow |
|
P, MW |
Q, Mvar |
||
Sovietsko-Sosninskaya –
Chapaevka |
220 |
232 |
128 |
Sovietsko-Sosninskaya – Parabel |
500 |
50 |
185 |
It is possible to
redistribute power flows between 220kV and 500kV overhead lines correctly by
using of the phase shifter device (PSD) installed on
Sovietsko-Sosninskaya substation. Technical characteristics of PSD are
presented in table 3.
Table 3 – Technical
characteristics of PSD
Name of
parameter |
Parameter value |
Capacity, MWA |
226 |
Permissible
current in OL, A |
787 |
Phase shift
(angle) of voltage, electrical degree |
±40 |
±15 |
|
Ratio step,
electrical degree |
2,67 |
Time of phase
shift (angle) changing (no more), s |
0,02 |
Generally, the PSD consists of two transformers: regulated T1 and series T2, which produces the
additional voltage vector, directed to the voltage vector at the beginning of
the overhead line perpendicularly and forms the phase shift relatively to the
main voltage (figure 2).
Figure 2 – The scheme of PSD
Under varying of
voltage on series winding by regulated transformer, the vector rotation of
total voltage at the beginning of an overhead line is accomplished.
Consequently, under changing of a power flow, transmitted through the line,
controlling a voltage phase at the beginning and in the end of the line is
possible [2].
The regime
calculation of interconnected network with PSD installed on
Sovietsko-Sosninskaya substation has been done by means of RastrKZ software. Phase shifter device is modeled by
including CT ratio: ÊÒ/r, ÊÒ/i – the real and imaginary components of CT ratio (figure 3).
Figure 3 –
Modeling of PSD in RastrKZ software
CT ratio is determined by
formula (1):
(1)
where δ – is the shift
angle between vectors of voltage, electrical degree.
Originally, the
resistance of PSD branch is assumed to be zero, that is corresponded the CT
ratio equals 0.99 ± j0.046.
Under changing the
value of CT ratio, power flows are forcibly redistributed from 220 kV to 500 kV
to optimal values (table 4).
Table 4 – The flux transfer by
means of PSD
Phase shift angle between voltage vectors |
Total power losses, MVA |
Power flows, MVA |
||
Sovietsko-Sosninskaya–Chapaevka (220 kV) |
Nizhnevartovsk PP–Sovietsko-Sosninskaya (220 kV) (by two circuits) |
Sovietsko-Sosninskaya–Parabel
(500
kV) |
||
0 (phase shifter device does not operate) |
54,1+j635 |
98-j14 |
230-j128 |
-50+j136 |
+2,67 |
53,5+j633 |
78-j4 |
220-j122 |
-60+j139 |
+5,34 |
53,3+j632 |
56+j0,1 |
208-j118 |
-71+j140 |
+10,68 |
54+j635 |
16+j14 |
188-j106 |
-92+j141 |
+16,02 |
56,5+j646 |
-24+j28 |
168-j92 |
-112+j141 |
+21,36 |
60,6+j664 |
-62+j44 |
76-j78 |
-132+j140 |
+24,03 |
63,4+j676 |
-80+j52 |
142-j62 |
-142+j139 |
+32,04 |
74+j722 |
-132+j80 |
120-j22 |
-170+j136 |
+37,38 |
82,9+j762 |
-164+j58 |
108+j10 |
-187+j133 |
+40,00 |
87,7+j782 |
-178+j104 |
104+j26 |
-195+j131 |
Based on these
results, it is concluded that the PSD optimal switching angle is approximately
11 electrical degrees. Under this angle 220kV power lines will detrain but
500kV power line will load while total power losses will identical with the
case when PSD does not operate.
References
1. About scheme
and program of Tomsk power system future development for the period 2013-2017
[Official site of Tomsk region Administration]. URL:
docs.pravo.ru/document/view/26481664/26384921 (date of circulation 17.08.2013).
2. Stelmakov V.N. Phase shifter device with thyristor adjustment
// Electricity.-2010.-¹8.-P. 20-23.