Òåõíè÷åñêèå
íàóêè/5. Ýíåðãåòèêà
Candidate of Science N.L.
Batseva, student Yu.P. Zagainova
Tomsk Polytechnic University,
Russia
The analysis
of the generators dropping effectiveness as the control action for
Sayano–Shushenskaya hydro power plant transient stability improvement
Nowadays the
capacity of Sayano–Shushenskaya hydro power plant (HPP) is 6400 MW, but the
power output is limited because of transfer capability deficit of the
transmission lines 500 kV Sayano–Shushenskaya HPP – Novokuznetskaya and
Sayano–Shushenskaya HPP – Oznachennoye. Restrictions are imposed according to
the transient stability retention of Sayano–Shushenskaya HPP generators.
Therefore the analysis of Sayano–Shushenskaya HPP generator transient stability
and the control action effectiveness under reference incident showed in [1] is
outstanding.
The main task of
the transient control in any power system (PS) is change-over PS to stable post
emergency conditions by means of the control action.
The information
parameters for the control action choice are determined in each case by
particular conditions and tasks, among them it is possible to single out the
typical kinds of the information used in the most cases [2, 3]:
1. Information about
the PS scheme and the regime under before emergency conditions: calculation correctness
depends on the accuracy which the basic elements of PS are described with –
primarily generators with regulation systems and loads.
2. Information about
disturbances: for the organization of sustainable control providing PS
stability it is necessary to know the destabilization reasons and the most
typical kinds of disturbances which cause problems. The typical disturbances
disrupting PS transient stability are short circuits.
3. Information about
emergency power imbalance: power imbalance must be such as power flows in any
other cross-sections do not exceed emergency permissible values during the
control action.
The most widely
spread control action applied in HPP is the generators dropping by means of
high maneuverability of hydroelectric units which is determined by the wide
range of power changing and short start time. The generators dropping provides
the rise of the steady-state stability level under post emergency conditions,
influences the control action conditions and it is realized by disconnection of
a generator or block circuit-breakers with a minimal delay with reference to
the moment when emergency disturbance is appeared [2]. The appearance of
increased load upon a foot bearing and a generator field winding should be
referred to the generators dropping negative effects. Therefore the cycle life
(frequency of the dropping and switching on) of generators is limited.
Figure 1 shows the
position of generator and turbine power-angle curves under normal, emergency
and post emergency conditions when generators are dropped.
Figure 1 – Generator and
turbine power-angle curves
After short
circuits the power imbalance appears between turbine mechanical power and
generator electric power in consequence generator rotor speeds up. The
generators dropping reduces turbine power thereby the available power imbalance
is diminished. Due to this diminishing the break function area increases and in
case of fast generators dropping speed-up area reduces. This fact allows keeping
synchronism of remaining generator parallel work with PS.
At the first stage
it is necessary to avert a destabilization: in other words to quantify dropped
generators on the basis of the most credible development of the accident
scenario.
At the second stage
(after removal of a disturbance) to identify the post emergency situation and
if it is required to produce the additional generators dropping for averting of
a destabilization.
For the analysis of
the generators dropping effectiveness the scheme of Khakasskaya PS has been
simulated in RUStab software and the most serious normative disturbance (group
III) – transmission line 500 kV Sayano–Shushenskaya HPP - Novokuznetskaya
tripping with the help of stuck breaker protection during the one-phase short
circuit close to 500 kV Sayano–Shushenskaya HPP busbar with the stuck breaker
phase fault in 500 kV Sayano–Shushenskaya HPP switchgear has been
distinguished.
Figure 2
demonstrates the result dependences.
Figure 2 – The regime of transmission line
Sayano–Shushenskaya HPP – Novokuznetskaya one-phase short circuit, clearing of
transmission line with the help of stuck breaker protection with a phase fault
of stuck breaker, unsuccessful one-phase automatic reclosing, generator
capability – 5100 MW
At the moment of
the short circuit the generator active power reduces to 480 MW, then power
fluctuations are happened in wide range; the generator rotor angle rises and at
3.12 seconds from the beginning of the process the first generator crank is
happened, then the growing excess torque which is caused the difference between
turbine and generator power begins to influence the rotor. This process leads
to the further angle rising. When the rotor speed is higher than the synchronous
one the slip s is appeared. The slip rises with the increasing of
the diversity between the rotor angle speed and the stator magnetic field.
For the generator
pulling into the synchronism after the first crank Sayano–Shushenskaya HPP
generator load shedding is necessary. It is provided by the generators dropping
(Figure 3).
Figure 3 – The regime of transmission line Sayano–Shushenskaya HPP –
Novokuznetskaya one-phase short circuit, clearing of transmission line with the
help of stuck breaker protection with a phase fault of stuck breaker, successful
one-phase automatic reclosing, dropping of 2 generators, generator capability –
5100 MW
According to Figure
3 at the moment of time equals to 4.5 seconds Sayano–Shushenskaya HPP
generators dropping ¹3 and ¹4 is appeared, the power imbalance is reduced, the
amplitude of the power oscillations is decreased, but the steady regime is not
achieved. This process shows that the control action is not enough, therefore
the additional generators dropping is needed (Figure 4).
Figure 4 – The regime of transmission line Sayano–Shushenskaya HPP –
Novokuznetskaya one-phase short circuit, clearing of transmission line with the
help of stuck breaker protection with a phase fault of stuck breaker, successful
one-phase automatic reclosing, dropping of 4 generators, generator capability –
5100 MW
Figure 4 shows that
at the 9th second from the beginning of the process the transient is
accomplished, the slip transition above zero is showed that the transient
stability is achieved, in other words 4 generators dropping provides the
transient stability during the parallel operating between Sayano–Shushenskaya
HPP and Khakasskaya PS.
References