Development of mining industry requires the leadthrough of reconstruction of operating mines. In this connection there is of interest research of the operating productivity of facilities of the boring drilling, providing maintenance of certain levels of speed of driving of barrels in combination with the applied equipment for loading of breed and fastening of making in the breeds of different fortress.

At the fixed time of cycle and driving of barrel by the diameter of D = 8 m is in driving, fastened by a concrete, in breeds with the coefficient of fortress on the scale of professor M.M. Protod'yakonov of f = 12 in the case of observance of the productivity of facilities of loading of Ð = 2 m3/hour (from a calculation in an array) breeds and fastenings K = 1,5 m3/hour of the put concrete (variant of terms of à1, table. 1) at speed of driving of table of v = 10 m/month there will be the enough productivity of facilities of the boring drilling - B = 15,15 m/hour.

 

Table 1.

Productivity of facilities of the boring drilling, B, m/hour, at f = 12

 

Variants

 

Ð,  m3/hour

K,   m3/hour

Speed, m/month

 

10

15

20

25

30

35

40

45

50

a1

2

1,5

15,15

-

-

-

-

-

-

-

-

a2

10

1,5

3,51

6,89

13,25

29,72

173,5

-

-

-

-

a3

20

1,5

3,21

5,8

9,73

16,4

30,22

75,9

-

-

-

a4

2

3

9,48

-

-

-

-

-

-

-

-

a5

10

3

3,09

5,41

8,7

13,7

22,09

39,44

96,01

-

-

a6

20

3

2,85

4,72

7,03

9,95

13,78

18,98

26,5

38,29

59,44

a7

2

5

8,24

-

-

-

-

-

-

-

-

a8

10

5

2,94

4,99

7,65

11,24

16,37

24,3

38,14

68,5

188,5

a9

20

5

2,72

4,39

6,32

8,6

11,31

14,6

18,68

23,85

30,65

 

Other things being equal, but sharp increase of the productivity of facilities of loading to Ð = 10 m3/hour in an array, that presents complication already, a situation suffers the followings changes (variants à2, table. 1): at v = 10 m/month it is necessary B = 3,51 m/hour.

The use in this variant of terms of high yield of facilities of loading, even in combination with the low productivity of fastening, allows to provide maintenance of speed of driving of barrel in a few more wide range of values.

The results of calculations show that the defined values of speed of driving of barrel can be provided with combination different (especially at the not too high values of v) on a size B, Ð, K: so, for example, speed of driving of 20 m/month can be supported:

- at B = 13,25 m/hour, Ð = 10 m3/hour and K = 1,5 m3/hour (middle productivity of the boring drilling, high enough loadings and low fastenings);

- at B = 9,73 m/hour, Ð = 20 m3/hour and K = 1,5 m3/hour (low productivity of the boring drilling, ever-higher loadings and low fastenings);

- at B = 7,03 m/hour, Ð = 20 m3/hour and K = 3 m3/hour (low productivity of the boring drilling, ever-higher loadings and middle fastenings);

- at B = 7,65 m/hour, Ð = 10 m3/hour and K = 5 m3/hour (low productivity of the boring drilling, high enough loadings and high fastenings);

- at B = 6,32 m/hour, Ð = 20 m3/hour and K = 5 m3/hour (low productivity of the boring drilling, ever-higher loadings and high fastenings).

Thus, within the framework of considered by us the fixed terms there are 6 alternative possibilities of providing of speed of driving of barrel of 20 m/month at f = 12. At planning or direct conduct of works can be given preference to combination of B, P and K, which in a greater measure corresponds to the concrete terms (presence and technical descriptions of equipment, his good condition, preparedness of workers etc.).

Results of calculations at f = 18 (table. 2, variants b1-b9) testify to the similar tendencies of change to the productivity of facilities of the boring drilling, but in this case for achievement of analogical speeds of driving of barrel more high values B  will be needed.

 

 

Table 2.

Productivity of facilities of the boring drilling, B, m/hour, at f = 18

 

Variants

 

Ð,  m3/hour

K,   m3/hour

Speed, m/month

 

10

15

20

25

30

35

40

45

50

b 1

2

1,5

22,63

-

-

-

-

-

-

-

-

b 2

10

1,5

5,25

10,29

19,8

44,39

-

-

-

-

-

b 3

20

1,5

4,79

8,66

14,53

24,5

45,15

113,42

-

-

-

b 4

2

3

14,16

-

-

-

-

-

-

-

-

b 5

10

3

4,61

8,09

12,99

20,42

33

58,9

143,4

-

-

b 6

20

3

4,25

7,05

10,5

14,87

20,58

28,4

39,6

57,19

88,79

b 7

2

5

12,31

-

-

-

-

-

-

-

-

b 8

10

5

4,39

7,45

11,42

16,79

24,46

36,3

56,98

102,3

-

b 9

20

5

4,07

6,56

9,45

12,85

16,9

21,81

27,9

35,6

45,78

 

Thus, analysis of change to the operating productivity of facilities of the boring drilling of øïóðîâ, to providing maintenance of certain levels of speed of driving of barrels, executed for the wide range of terms, rotined the following:

- the productivity of facilities of the boring drilling  exponentially increases with the increase of level of speed of driving of making;

- the certain level of driving speed can be attained by different combination of the productivity of facilities of the boring drilling, loadings and fastenings, here, to the certain limit, there is a great number of variants of providing of one or another speed;

- joint influence of the productivity of facilities of loading and fastening is able to provide maintenance of this speed of leadthrough of making at more low (in a number of cases to 15 times) values of the productivity of the boring drilling;

- at growth of coefficient of fortress of breeds for providing of this speed of driving it is necessary to increase the productivity of facilities of the boring drilling.